  1. Analysis

    More objections do not prove the right to object is too broad

    TenneT reports a doubling in objections and warns of years of delay. Two days later, the Council of State dismissed every appeal against the Rijswijk to Leiden heat pipeline. Read together, these two reports from the same week tell a different story than either does alone.

    Read more →
  2. Policy

    From today, grid congestion reaches small consumers too: capacity becomes a question of allocation

    As of 1 July 2026, the automatic priority for small consumers on the electricity grid disappears. Grid congestion thereby shifts from a problem affecting a handful of large industrial parties to one touching the whole of society, making it, above all, a stakeholder management challenge.

    Read more →
  3. Knowledge Base

    Six lessons from the ACM review: why transparency is essential for grid expansion

    The ACM concluded that the investment plans of Enexis, Liander, Stedin and TenneT were insufficiently substantiated. The network operators are launching an improvement programme. Six lessons on transparency and stakeholder communication that go beyond the investment plan itself.

    Read more →
  4. Analysis

    Grid reinforcement delayed: why stakeholder and environmental management makes the difference

    Sixty percent of TenneT's grid expansion projects face an average delay of two and a half years. Better stakeholder and environmental management is the key to acceleration.